If you program a periodical Generator test run, while the system is connected to the Shorepower, can you switch to use the Generator power?

Shore is on AC1IN
Gen is on AC2IN

CCGX Color Controlgen start
2 |3000

Up to 8 attachments (including images) can be used with a maximum of 190.8 MiB each and 286.6 MiB total.

1 Answer
Alexandra avatar image
Alexandra answered ·
3 comments
2 |3000

Up to 8 attachments (including images) can be used with a maximum of 190.8 MiB each and 286.6 MiB total.

harold avatar image harold commented ·
I know, but that's not what I want in normal shore operation.
0 Likes 0 ·
Matthias Lange - DE avatar image Matthias Lange - DE ♦ harold commented ·
AC IN 1 has priority over AC IN 2.

If both are connected the system will always use AC IN 1. To use AC IN 2 you need to disconnect AC IN 1 or you give a signal to the Quattro and program it to ignore AC IN 1 in that case.

But the easiest way would be to just swap them. What do you think is the problem with that in normal operation?

0 Likes 0 ·
harold avatar image harold Matthias Lange - DE ♦ commented ·
Thanks,

During normal operation, I don't want the generator to start due to the programmed 'conditions'
So ignore when AC1 excists

Maybe I just let the testing period idea go ;-)