question

beavis avatar image
beavis asked

System wiring confirmation

Here is picture how I have planned my system connections. Only power connections drawn monitoring and Cerbo missing in here. Do you see any mistakes or am I missing something?
1688203536717.png

wiring diagram
1688203536717.png (150.7 KiB)
2 |3000

Up to 8 attachments (including images) can be used with a maximum of 190.8 MiB each and 286.6 MiB total.

1 Answer
Sarah avatar image
Sarah answered ·

Hi @beavis at a high level it looks good. If the budget can stretch I would consider a second shunt configured as a dc load meter so that you get accurate dc loads connected on the negative 24 volt Orion connection, a battery isolation switch, and possibly Orion load, Phoenix charger, and mppt solar isolation switches, I haven’t used them but depending on the type of batteries you might also benefit from installing a battery balancer to optimise the battery performance.

2 |3000

Up to 8 attachments (including images) can be used with a maximum of 190.8 MiB each and 286.6 MiB total.

Related Resources

Additional resources still need to be added for this topic