Battery expansion

Every time I had to expand an existing system, measuring the battery voltage with a multimeter was the chosen way.

I did my best to match old/new packs within 0.1-0.2V and all was perfect. Of course, a little current will flow between old/new packs.

Sometimes, old packs were at 100% SOC, in this case, switched off the system, disconnected old one, connected new one, switched on the system and charge it to 100% SOC. After that, switched off the system, set the DIP switches as required (defined the master) and switched ON all packs and the system.

Other times when old pack were not fully charged I opted to discharge it and voltage match with new pack, followed by system shutdown, DIP switch setup and turn ON all.

Most batteries are supplied at roughly 60% SIC, as they can be stored for a long time at that level. Since the voltage curve is very flat in that range, newly purchased batteries can be connected almost straight away.

A) Switch on each battery individually and measure the voltage at its terminals, then charge or discharge the system to the same voltage, e.g. via the ESS/Grid Setpoint.

B) Buy a small 60V/5A bench power supply and use it to charge them. Depending on the BMS, however, the batteries may shut down if they don’t receive a heartbeat via the BMS data connection. I don’t know Pytes.