G100/2 Compliance. Multiplus-II & Quattro's

The decision has been made not to gain G100/2 compliance. The decision was made based on our historic sales numbers prior to G100/2, the engineering time required and the commercial reward.
We do of course have G98 & G99. If feeding in to the Grid is required then the most popular option is to use the 5KVa models, configfure to Grid code G98 restricting the feed in and load out to 3.68Kw.