Hi all,
I’m running a 3-phase setup with a Multi RS Solar 48/6000, controlled by a Cerbo GX. I have several PV strings connected directly to the Multi RS (DC-coupled), and I’m using DESS trade mode.
Overall, the system works very well. It manages energy flows quite intelligently — charging the battery from the grid during low prices and discharging/exporting during high prices.
However, I’ve noticed something that doesn’t seem optimal: my PV production is being limited, even when more solar power is available, while at the same time grid-to-battery charging is active. This makes it appear that grid charging is being prioritized over PV charging.
From a logical perspective, I would expect the following priority in energy flows:
-
PV should first cover local consumption
-
Any excess PV should go to charging the battery
-
Grid energy should only be used to supplement this, charging the battery up to the configured maximum grid import and battery charge limits
Since PV energy is essentially free, it seems inefficient to limit PV while importing energy from the grid to charge the battery. In my view, the only exception would be during negative energy prices, where it makes sense to prioritize grid charging and potentially limit PV production.
My questions:
-
Is this behavior expected in DESS trade mode?
-
Is there a way to influence this priority without using complex Node RED settings?
-
Or is this a known limitation that might be improved in a future update?
Curious to hear if others have seen the same behavior or have found ways to optimize this.
In the images below, an example is shown of PV output being limited, starting exactly at 12:00 when grid-to-battery charging begins.
Thanks!