Hello
Can I connect 3 single phase inverters to a GX with a lithium battery bank?
WIth each inverter have a separate AC input and output?
The issue is to manage a group of panels and battery controlled by BMS with a cerbo on 3 separate inverters for 3 houses that have independent single phase AC input?
Can the GX see the 3 inverters as separate units and manage them.
Thanks
It is not supported to do that. Independent systems need their own battery and gx. You can monitor a second inverter with a gx but terms and conditions apply as per the manual.
A gx can manage one inverter/battery combo.
Thanks for answering