How to set static import and export on 3 Phase MultiPlus-II 48/5000/70-95 120V

I have a 3 phase 120/208V setup of MultiPlus-II 48/5000/70-95 120V on the latest firmware with Cerbo GX. I do not have any external meter and it is difficult to install one, so I am trying to setup very simple important and export rules.

All I want the system to do:

  1. Import 10kW from the grid from 9A-4PM until battery is full.
  2. Export 10kW from the grid from 4PM-9PM until the battery is empty.

Anyone know how to do this? I have tried the ESS assistant, but I don’t think it can do this?

Thanks!

I’m far from an expert, but… I’d try to set the grid setpoint accordingly in ESS, that should be possible via ModBus or MQTT or NodeRed, and go from there.

I got the Node Red set up, but changing the Grid set-point from 30W => 1000W or -1000W doesn’t do anything. Any one else know what might cause the system not to react to grid set-point change?

Have you set on the GX under ess feed in from dc enabled? You can also limit feedback there and set your min SOC
If you have a shedules for feedback and charge do that with node red.