They even ran a new line for him but he is literally on a best effort basis. Just too far and a new transformer is not feasible for just one customer. Unless he agrees to support the cost of over 100K euros, given this is a mountain area.
That’s 3 large MPs. What is the intended load? If the voltage is that low already, what does it drop to when you connect say 2kW kettle, or an oven, or both on a single phase.
If you dont need 3 phase in I’d be tempted to request single phase on L1, which would enable the supplier to double up the conductors, assuming you’re star fed.
It doesnt make much sense that one phase is that much higher at no-load. That can only happen if the source transformer is too small and your neighbours are pulling power.
There is a heat pump on load side. Forgot to mention there are 50kw solar panels and a Fronius Tauro. During the day there will be no issues. Trouble is how to use this poor network during night to get at least something out of it.
Then the priority here is ALWAYS charging the batteries to supply the load or to be able to continue working OFF-grid if the grid fails and let the PV inverter work …
Then the small 3kw chargers per phase would be far too few. They could be cascaded as in telecommunications technology, but that would be infinitely expensive
A generator would almost be better … because they are quattros anyway
There are Rackmounted Sollutions with up to 30kw per phase …