I am a DIY guy with this project - Two Multiplus II 48/5000/75-50 installed in parallel and connected to two 48V 280Ah Docan power Lithium batteries with Daren BMS (each) also in parallel. Three PV panel systems connected to three Victron smart Chargers. Victron Lynx distributer used for cable connections. All connected to my Raspi 4b with can bus hat and Ve-direct cables for monitoring.
I am now hoping to program the system with ESS but with no feed-in and connected to an energy meter ET112. Since I am located in Malta, there is no country code for us and I think that the “None” grid code should be applied. I require some assistance in this regard and advise if there is a problem in this type of system setup. Can any body help?