Hello everyone, here is my schematic of the ESS installation in France that I’m currently working on. I’d like a fresh pair of eyes to check whether what I’m doing is correct and that there are no major errors. Also, I’d like to install a car charger. Where should I connect it, before or after the MultiPlus? The BMV712 display and the isolator, which also disconnects the batteries’ negative terminals, are missing from the schematic. I plan to replace them with 20 kW lithium batteries. Thanks for your feedback.
Protection and isolation must be double-pole, including on the MultiPlus, and on both sides of the solar charge controller.