No, that’s new to me; I’m curious to see when it gets released as Stable.
I’ve now connected my Growatts via Waveshare RS485 as well as the ShineX units, so I can get them into evcc.
That worked surprisingly smoothly, and then I had the idea that, with Modbus, they should surely be able to connect to Victron VRM too. Then I could use the solar forecast as well.
When I searched the forum and Google, most of the results were about three-phase systems that also had the display issue, so I’m just not sure whether I’m heading into a dead end.
I understand its 3 phase, correct?, L1/2/3 as written.
Or, even when mono phase, as above said the 1:1 rule towards the Victron inverter…pending settings in the Growatt inverters…and yes, these can be bigger but are limited in their output (winter setup that is called).
The easiest way and bomb-proof is to use a 3 phase Victron or a Carlo Gavazzi meter as that shows up without all the tangle and headaches when you program them as PV inverters (what shows in the mimic has to be seen, pending the GX and it’s firmware again).
You can use any 3 phase meter as 3 mono inputs/outputs and program these accordingly also…
Yesterday evening, I still had a glimmer of hope that a misconfiguration in the Cerbo (loads connected to AC-in and AC-out instead of just AC-in) might be the cause.
But it makes no difference, apart from making the panel look tidier.
I think I’ve just got it working. I turned the single-phase Growatts in Node-Red into three-phase ones and changed the calculation formula for L2 and L3 respectively…