Feature request for Scheduled charge levels

Dynamic ESS does not work well for our system because the power demand varies too widely. Scheduled charge levels are therefore a better fit.

It would be very useful to enhance scheduled charge levels as follows:

  • Show details of all schedules, not just the active schedule.
  • Allow two or more schedules to be active at the same time.
  • Provide easier access to scheduled charge levels without requiring users to navigate through Settings > System Setup > ESS > Scheduled Charge Levels.

What do you mean by that? What would the function be? Or how would it add functionality?

Schedule multiple charging periods when grid prices are lower. For example, the first period could run from 1 pm for one hour, and the second from 11 pm for two hours.

Currently, you can select only one charging period per day.

You can use DESS for that.

As far as I know, DESS is fully automated, so you cannot control charging times or battery levels manually. Or am I wrong?

Times no. But in the local system there is some control.