For my application I need a grid code set (NZ) to comply, simply because it’s normally wired to our grid. I also have the ESS assistant enabled.
If I disconnect the unit from the grid temporarily and place it in “charger only” mode with power provided by a conventional generator, does the quality of power still need to meet the grid setting?
As a follow-up question, my application uses only the Multiplus II GX and a 48V LFP battery, no PV or export. It will replace a generator and be used in a similar fashion - commanded remotely to run in “inverter only” mode only when needed and without having to provide a “failover” or UPS-type function. Same with charging the battery - I’ll use “charger only” mode (on grid power) and manage the SoC externally.
All that begs the question- do I benefit from having the ESS assistant?
Ok, so “charger only” mode doesn’t insist on the waveform characteristics matching the set grid code. Although I can easily cancel the set grid code as I know the password, that’s just one more step needed in the rare case I might need to charge the battery without mains power. I doubt I will ever need to do that but I want to understand my options.
Yes, I only installed the ESS assistant because I thought that was a requirement but I can see now that it’s not needed since I’m not trying to manage overall system power flow among PV, a battery and export.
I made a schematic of the overall wiring and and ‘truth table’ of the basic functioning. It’s just a battery + MP2 powering a rainwater pump in the rare case mains power is out. I don’t need the MP2 to pass power through when mains is present, nor do I need a “UPS” failover function. The inverter will only (a) charge the battery periodically and (b) power the pump when needed if mains is ‘off’, both directed externally using Modbus by my own controller. This is all built and functioning, I’m just fine-tuning the software.
a) I’m thinking I don’t have any need for the features in the ESS assistant so might remove it. I don’t plan to install PV or export power.
b) Since this system replaces a generator and ATS, that item will become ‘surplus to requirements’ but I might keep it on hand if it’s useful in the case of an extended power outage for manually charging the battery. I don’t want to spent money on a DC charger if I can use the MP2 on a temporary basis. If I don’t have to return the grid code back to “none”, that simplifies the work to just wiring it up. I already know my grid code pw.