There is a good document how to realize a setup with Ziehl for a Multiplus 8k/10k/15k in parallel setup: 3. Installation
If you like to bypass Multiplus due to maintanance or broken hardware, there are 2 options to allow the power from grid to loads:
- Using 2x mechanical bypass switches (grid → loads or grid → 2x relais → loads)
- Add a 3-position switch to control relais K2 (1-from AUX relay, 0-off, 2-230V power). In position 2, the relay is activated.
To disable AC-out, you need to switch of the 4p breaker / RCD.
May be, a double channels to this 3-position switch is required to disable ground (N–PE) relay.
What do you think about a 3-position switch? Is it already applied?